Setup matrix
============

A setup matrix defines the time and cost of setup conversions on a resource.
Within a setup matrix rules are used to define the changeover cost and
duration.

To compute the time of a changeover the algorithm will evaluate all rules in
sequence (in order of priority). For a rule to match the changeover between
theoriginal setup X to a new setup Y, two conditions need to be fulfilled:

* | The original setup X must match with the fromsetup of the rule.
  | If the fromsetup field is empty, it is considered a match.
* | The new setup Y must match with the tosetup of the rule.
  | If the tosetup field is empty, it is considered a match.

The wildcard characters \* and ? can be used in the fromsetup and tosetup
fields. As soon as a matching rule is found, it is applied and subsequent
rules are not evaluated. If no matching rule is found, the changeover is
not allowed.

For instance, consider a setup matrix with the following rules:

========== ======= ======= ==========  =====
Priority   From    To      Duration    Cost
========== ======= ======= ==========  =====
1          \*green \*green 0           10
2          \*red   \*red   0           10
3          \*green \*red   1 day       50
4          \*green         2 day       50
5                          3 day       50
========== ======= ======= ==========  =====

Based on this matrix:

- A change from “lightgreen” to “darkgreen” takes no time, but costs 10.
  Rule 1 applies.

- A change from “green” to “black” takes 2 days and costs 50. Rule 4 applies.

- | A change from “red” to “black” takes 3 days and costs 50. Rule 5 applies.
  | Without rule 5 this changeover would not be allowed.

**Fields**

============ ================= ===========================================================
Field        Type              Description
============ ================= ===========================================================
name         non-empty string  | Name of the setup matrix.
                               | This is the key field and a required attribute.
rules        list of setup     A read-only list of rules in this matrix.
             matrix rules
action       A/C/AC/R          | Type of action to be executed:
                               | A: Add an new entity, and report an error if the entity
                                 already exists.
                               | C: Change an existing entity, and report an error if the
                                 entity doesn’t exist yet.
                               | AC: Change an entity or create a new one if it doesn’t
                                 exist yet. This is the default.
                               | R: Remove an entity, and report an error if the entity
                                 doesn’t exist.
============ ================= ===========================================================

**Methods**

+-----------------------------+----------------------------------------------------------+
| Method                      | Description                                              |
+=============================+==========================================================+
| addRule(priority=[integer], | This method adds a new rule to the matrix.               |
| fromsetup=[string],         | Only the priority keyword is compulsory. The other       |
| tosetup=[string],           | arguments are optional.                                  |
| duration=[timeperiod],      |                                                          |
| cost=[number])              |                                                          |
+-----------------------------+----------------------------------------------------------+

Setup Rule
----------

Within a setup matrix rules are used to define the changeover cost and duration.

The rules are evaluated in sequence, starting with the lowest priority number.

============ ================= ===========================================================
Field        Type              Description
============ ================= ===========================================================
priority     integer           | The priority of the rule.
                               | This is the key field.
fromsetup    string            | The previous setup.
                               | If the field is empty the rules applies to any previous
                                 setup value.

                               Wildcard characters are allowed in this string: \* matches
                               a sequence of characters, and ? matches a single character.

tosetup      string            | The new setup.
                               | If the field is empty the rules applies to any new
                                 setup value.
                               | Wildcard characters are allowed in this string, similar
                                 as in the fromsetup field.
duration     timeperiod        Duration of the changeover.
cost         double            Cost of the changeover.
============ ================= ===========================================================


**Example XML structures**

Adding or changing setup matrices

.. code-block:: XML

    <plan>
      <setupmatrices>
         <setupmatrix name="Painting line changeover">
           <rules>
             <rule priority="1"
                fromsetup="green" tosetup="red"
                duration="P0D" cost="10" />
             <rule priority="2"
                fromsetup="red" tosetup="green"
                duration="P0D" cost="10" />
             <rule priority="3"
                fromsetup="white" tosetup="black"
                duration="P10D" cost="50"/>
             <rule priority="4"
                fromsetup="black" tosetup="white"
                duration="P10D" cost="50"/>
             <rule priority="5" fromsetup="yellow"
                duration="P2D" cost="20"/>
             <rule priority="6" tosetup="yellow"
                duration="P2D" cost="20"/>
             <rule priority="6"
                duration="P3D" />
           </rules>
         </setupmatrix>
      </setupmatrices>
    </plan>

Deleting a setup matrix

.. code-block:: XML

   <plan>
     <setupmatrtices>
       <setupmatrtix name="changovers" action="R"/>
     </setupmatrtices>
   </plan>

**Example Python code**

Adding or changing setup matrices

::

    matrix = frepple.setupmatrix(name="changeovers for paint line")
    matrix.addRule(priority=1, fromsetup="*green", cost=10)

Deleting a setup matrix

::

    frepple.setupmatrix(name="changeovers for paint line", action="R")

Iterate over setup matrices and setup matrix rules

::

    for m in frepple.setupmatrices():
      print "Matrix '%s' has the following rules:" % m.name
      for i in m.rules:
        print " ", i.priority, i.tosetup, i.fromsetup,
        print i.duration, i.cost