Modelling concepts
==================

| Concepts as items, locations, customers, demands, ...don’t need a much of
  an explanation.
| The modelling concepts of operations, material and capacity consumption
  however need some introduction.

**Operation**

The key modelling element is an operation, which defines an activity.

There are different operation types:

* fixed time: the duration is identical regardless of the planned quantity.
  Eg, a transport operation

* time-per: the duration increases linearly with the planned quantity.
  Eg, a manufacturing operation

* routing: this operation type represent a sequence of sub-operations.

* alternate: an alternate operation models the choice among multiple choices.

| Example:
  Operation “Make product X” takes 10 minutes per unit.

.. image:: _images/modelling-1.png
   :alt: Modeling - Operation

**Buffer**

Items are stocked in buffers. A buffer, often called SKU -stock keeping unit-,
is a (physical or logical) inventory point.

There are different buffer types:

* default: a buffer that is replenished with a producing operation

* procure: a buffer that is replenished with a procurement operation

* infinite supply: a buffer without replenishing operation

| Example:
| Buffer “Part A” models inventory of the item “part A” in location “my factory”.
| Buffer “Part B” models inventory of the item “part B” in location “my factory”.
| Buffer “Bulk product” models inventory of the item “bulk product” in location “my factory”.

.. image:: _images/modelling-2.png
   :alt: Modeling - Buffer

**Flow**

Operations consume and produce material through flows.

A flow defines an association between the operation and a buffer. Flows thus
represent the Bills of Material (aka BOM) and Bills of Distribution (aka BOD)
in your model.

There are 2 types of flows:

* start: Flows happening at the start of the operation. These are normally consuming
  material and have a negative quantity.

* end: Flows happening at the end of the operation. These are normally producing
  material and have a postive quantity.

| Example:
| Operation “Make product X” has 3 flows.
| A first flow to consume 1 units of a buffer “Part A” at the start of the
  operation.
| A second flow to consume 2 units of a buffer “Part B” at the start of the
  operation.
| And finally a third flow to model the production of 1 unit of “product X”
  when the operation finishes.

.. image:: _images/modelling-3.png
   :alt: Modeling - Buffer

**Load**

Operations also require capacity, which is modelled through loads. Capacity is
available in resources and a load defines an association between the operation
and a resource.

| Example:
| The resource “production line” is required to perform the operation.

.. image:: _images/modelling-4.png
   :alt: Modeling - Buffer

**Operationplan**

An operation only statically defines the activity, and doesn’t specify any
planned dates or quantities. Concrete activities are then instantiated in
operationplans.

| Example:
| To satisfy a customer demand we plan to run “Assemble product X” for 12
  units from tomorrow 8am till 10am.
| Another instance of “Make product X” is planned the next day from 3pm to 4pm
  for 6 units to meet another customer demand.
| Another instance of “Make product X” for 20 units is planned today to
  replenish a buffer storing the product X to its safety stock level.

**Putting it all together**

Combining all of the above modelling objects we can construct a network
representing the flow of material and usage of capacity in your plant.

The picture below shows a simple network with 3 levels.

.. important::

   Drawing this type of schematic network of your environment is extremely useful
   before you start entering data in frePPLe. Each shape and line in such a
   diagram will be defined as an input record in the frePPLe data model.

.. image:: _images/modelling-5.png
   :alt: Modeling - Buffer